Ordering concrete is expensive — too little means a split pour, too much waste. Calculate exact cubic yards for slabs, footings, or columns. Ratios included.
Use this reference to estimate concrete volume in cubic yards for common slab sizes. All calculations assume a standard 4-inch thickness. For thicker slabs, multiply by the ratio.
| Project Size | Area (sq ft) | Thickness | Cubic Yards | 80lb Bags Needed | Ready-Mix Cost |
|---|---|---|---|---|---|
| 10x10 ft Patio | 100 | 4 in | 1.23 | 55 | $165 |
| 20x20 ft Garage | 400 | 4 in | 4.94 | 222 | $650 |
| 24x24 ft Driveway | 576 | 4 in | 7.11 | 320 | $940 |
| 4x4 ft Footing | 16 | 12 in | 0.59 | 27 | $80 |
| 30x50 ft Foundation | 1,500 | 4 in | 18.52 | 833 | $2,450 |
Ready-mix concrete costs $100-150 per cubic yard delivered. For very small pours (under about 1 cubic yard), bagged concrete is usually the simpler choice — the break-even comparison below works through where the line sits. Always order 5-10% extra to account for spillage, uneven subgrade, and form adjustments.
Concrete is priced by the cubic yard but delivered by the truck, and that mismatch is where surprise charges come from. A standard mixer truck hauls 8–10 cubic yards per trip, so ordering 5 yards puts a half-empty truck on your driveway — and plants charge for the empty half one way or another.
One cubic yard is 27 cubic feet — a 3 × 3 × 3 ft cube — and at the standard 4-inch slab thickness it covers 81 sq ft. The volume table above turns that into order quantities for common projects; the quick mental anchor is that a single-car driveway, roughly 10 × 20 ft, takes about 2.5 yards at 4 inches.
Plants set a minimum load — commonly 2–4 cubic yards — and below it a short-load fee of roughly $15–25 per missing yard applies. The second meter is time: a truck is expected to discharge within about 10 minutes per load, after which waiting charges of $75–150 per hour can start. Both fees push small pours toward bagged concrete, and the break-even math is spelled out in the next section.
When you call, quote the wet (poured) volume from the calculator above — plants batch by yield and have the dry-volume conversion built into their per-yard price.
An 80 lb bag yields 0.60 cubic feet of mixed concrete, which is why a cubic yard takes 45 of them — the same per-yard count behind the bag column in the volume table above. At $5.50–6.50 per bag, bagged material runs about $250–290 per cubic yard, against roughly $135 a yard for ready-mix in the price range that table quotes. The price gap is not close; what decides small pours is everything the price leaves out.
The 10 × 10 patio in the volume table needs 1.23 yards: 55 bags come to roughly $300–360, against the $165 delivered price already listed — ready-mix wins by nearly half. The gap widens with size: the 24 × 24 driveway is 320 bags (roughly $1,760–2,080 of hand mixing) versus a $940 truck. The price break-even therefore sits at or below 1 yard, and every practical break-even above that is decided by scheduling and site access, not by arithmetic.
Bagged mix is a fixed recipe, while ready-mix is batched to your spec — air entrainment for freeze–thaw climates, fibers for crack control, the slump the finisher asks for. On structural pours the driver's batch ticket is also the paper trail an inspector may ask for; bags leave you with a stack of empty pallets instead. When you do buy bags, match them to the strength table above.
Concrete strength is measured in PSI (pounds per square inch) after 28 days of curing. Different projects require different minimum strengths. Using concrete that is too weak can cause structural failure, while over-specifying strength wastes money.
| Project Type | Min PSI Required | Recommended Mix | Common Uses | Curing Time |
|---|---|---|---|---|
| Non-structural | 1,500-2,000 PSI | 1:3:5 mix | Garden paths, fence posts, light-duty pads | 3-5 days light use |
| Residential Slabs | 2,500-3,000 PSI | 1:2:4 mix | Patios, sidewalks, garage floors, driveways | 7 days light use |
| Structural | 3,000-4,000 PSI | 1:1.5:3 mix | Foundation walls, footings, beams, columns | 14 days light use |
| High-Strength | 4,000-6,000 PSI | Engineered mix | High-rise buildings, bridges, heavy-load floors | 28 days full cure |
| Fiber-Reinforced | 3,000-4,000 PSI | 1:2:3 + fibers | Industrial floors, driveways, crack-resistant slabs | 7-14 days light use |
For most residential projects, 3,000 PSI concrete (standard 1:2:4 mix) is the sweet spot — strong enough for driveways, patios, and foundations, without paying for unnecessarily high strength. Always order ready-mix concrete with a 28-day strength test guarantee. In cold climates, specify air-entrained concrete to resist freeze-thaw damage. Use this concrete calculator to determine the exact volume needed for your project.
A slab that measures 100 cubic feet wet will not take 100 cubic feet of dry ingredients. Cement and sand fill the voids between aggregate, so the dry mix shrinks roughly 30–35% when water is added and compaction drives out the air. That is why the concrete formula multiplies the wet (poured) volume by a dry-volume factor of about 1.54:
If you order ready-mix instead of mixing on site, order by the wet (poured) volume the calculator gives you — the ordering section above covers exactly what to ask the plant when you call.
Concrete does not dry — it cures, a chemical reaction that keeps gaining strength for weeks. The curing column in the mix table above lists the light-use days per project type; here is what those numbers mean on the slab itself, and why the first two days are the one stage you cannot patch after the fact.
| Elapsed time | What the slab can take | Strength reached |
|---|---|---|
| 12–24 h | Nothing but the formwork — early footprints mark the surface permanently | ~10–15% |
| 24–48 h | Careful foot traffic; no ladders, no tools set down | ~20–40% |
| 7 days | Garden furniture, wheelbarrows, a car moved on carefully | 60–70% |
| 14 days | Light use on structural pours, per the mix table above | ~80% |
| 28 days | Full design load — vehicles, hot tubs, masonry walls | 100% (design strength) |
Strength comes from the reaction between cement and water, so the surface must stay damp for at least the first 7 days: mist it two or three times a day, keep it under plastic sheeting or wet burlap, or roll on curing compound the day after the pour. A slab that dries out on day 2 in the sun keeps its shape but not its rated strength — and hot, dry or windy weather pulls water out of the surface faster than the reaction can replace it.
Below about 50°F the reaction slows sharply — concrete at 50°F gains in 7 days roughly what it would gain in 3 days at 70°F — and if the water in fresh concrete freezes before it cures, the damage is permanent and shows up as flaking and scaling the first winter. That is why cold-weather pours rely on insulating blankets and enclosures rather than simply waiting longer. Match the calendar to the project type in the mix table above instead of a fixed number of days.
No more buying 5 gallons when you only need 3. Enter your room dimensions, subtract doors and windows, and get the exact gallons and cost. For one coat or two.
Running short on tiles halfway through is a nightmare. Get the exact count — including waste margin — for any room, any tile size. Know how many boxes to buy before you start.
How many bricks for that wall? And how much mortar? Enter your wall dimensions and brick size — we'll calculate the bricks, mortar volume, and bags of cement needed. 5% waste included.
Roofing material math is tricky — pitch changes everything. Enter your roof dimensions and get shingle bundles, squares, and underlayment rolls. Waste included so you don't come up short.
Too much mulch is a waste of money, too little looks unfinished. Get the exact amount — in bags or cubic yards — for your garden beds. Enter dimensions and depth, and we'll tell you what to buy.